Galena Mining Expects Abra mine processing plant completion ahead of schedule
- Galena Mining (G1A) expects to complete the construction of a processing plant at its Abra base metals mine in Western Australia ahead of schedule
- Today, the company reported construction progress reached 97 per cent completion as of November 30, and Galena expects practical completion this month
- Ore is being mined from underground and stockpiled, ready for processing in the new year when concentrate production is also due to begin
- Considering its “record underground development” in November and commissioning progress to date, G1A believes Abra is “on the verge” of a quick transition into production
- Company shares are up 13.5 per cent and trading at 21 cents at 3:56 pm AEDT